Between the end of construction and the commercial opening of a data center lies a short, decisive period: testing, punch-list closure, acceptance, handover to the operations team. This is where many delays and costly failures hide. And the commercial operation date is when the asset starts earning.

GridReadiness offers an independent commissioning readiness review: checking, before it is too late, that the site is really ready to operate.

WHAT ONE MONTH OF DELAY COSTS

Order of magnitude of rent for a wholesale-leased data center, based on €100 to €150 per IT kW per month:

IT capacityRent per monthThree months of delay
10 MW€1m to €1.5m€3m to €4.5m
50 MW€5m to €7.5m€15m to €22.5m
120 MW€12m to €18m€36m to €54m

Indicative estimate, excluding any contractual penalties to the tenant. Actual rents depend on market, density and contract.

WHAT GOES WRONG MOST OFTEN

The same situations recur from one project to the next:

Warning signs Tests run out of sequence or incomplete for lack of time
Hundreds of open punch-list items a few weeks before opening
A site operated before formal acceptance
An operations team hired late, not yet trained, without procedures
No spare parts, tools or signed maintenance contracts
Unqualified monitoring alarms that nobody can yet interpret

THE FIVE LEVELS OF TESTING

Data center commissioning usually follows five levels, from simplest to most complete:

LevelWhat is tested
1Factory acceptance tests of main equipment (transformers, UPS, generators, switchboards)
2On-site installation checks, conformity with drawings
3Start-up of each piece of equipment, one by one
4Functional tests of each system: power, cooling, fire safety, monitoring
5Integrated systems test: the whole site under load, with failure simulations (grid outage, loss of a generator or chiller)

Level 5 is the only one that proves the site meets its availability commitments. It is also the one most tempting to cut short when the schedule is tight.

WHAT WE CHECK

ItemIn practice
TestingRun in sequence, complete, results compliant and documented
Punch listHow many items remain open, which are critical, with what closure plan
Operations teamStaffing, training, procedures, on-call in place before opening
LogisticsSpare parts, tools, stores, maintenance contracts
High voltageSubstation energisation, protection settings, transformer testing
AcceptanceAccept now, accept with reservations, or wait?

WHEN TO ENGAGE

Ideally three to six months before the target operation date, with three checkpoints: before integrated testing, before acceptance, and before handover to operations. A one-off review is still possible later, for example at a lender's request before a drawdown.

DELIVERABLES

A readiness report with a clear opinion (ready, ready with conditions, not ready), the list of blocking issues, a dated action plan and a recommendation on acceptance. Follow-up until opening if needed.

WHO IT IS FOR

Lenders and funds, for whom the operation date drives revenue and repayment. Mid-size developers without a dedicated in-house team. Tenants who want to check the site will be ready on the promised date. See also our offer for lenders and funds.

OUR TEAM AND INDEPENDENCE RULE

The review is led by experts from the GridReadiness network who have led data center acceptance and commissioning, supported by our high-voltage experts. GridReadiness remains your single point of contact. We do not design, build or sell any equipment. When we support a developer, we do not review the same project for a lender. It extends our Readiness Manager role.

FREQUENTLY ASKED QUESTIONS

What is data center commissioning?

The period between the end of construction and commercial opening: five levels of testing, punch-list closure, acceptance, handover to the operations team.

Why an independent review?

Because the contractor and the operator both have an interest in hitting the date. An outside view checks that the site is really ready, before problems surface in operation.

When should it be planned?

Ideally three to six months before the target operation date, before integrated testing and before acceptance.