Cooling a data center with seawater instead of chillers or evaporative towers is attractive: it saves electricity and uses no freshwater. It remains rare in France. Data4's project in the port of Saumaty, Marseille, put to public consultation on 18 November 2026, brings it back into focus. Here is how this type of cooling works, what French rules say about discharges, and the questions an application should address.
THE PRINCIPLE
Seawater is pumped through heat exchangers, where it absorbs heat from a closed freshwater loop, then is discharged slightly warmer. The closed loop cools the server rooms. Seawater never touches the servers and no water is evaporated.
The process depends entirely on sea temperature. In Marseille, the Thassalia marine geothermal plant draws water at 7 metres depth, at about 14 °C in winter and 22 °C in summer. In summer this water alone is no longer enough to cool IT equipment: back-up chillers are needed, which use electricity and make noise.
WHAT ALREADY EXISTS IN MARSEILLE
- Marine geothermal energy for buildings. Thassalia (Engie) and Massileo (Dalkia, EDF group) have heated and cooled Euroméditerranée districts with seawater since 2016 and 2017.
- Former mine water for data centers. Digital Realty's port data centers have used water from the Galerie de la Mer, dug to drain the Gardanne mines, at about 15 °C all year, since 2021. It is not seawater, but the principle is similar.
- The Saumaty project. Conceived in late 2022 as a 7.5 MW floating barge by Nautilus Data Technologies, it was taken over in 2025 by Data4: a building with 22.5 MW of grid connection, partly over the sea, cooled by basin water with chiller back-up on hot days.
WHAT THE RULES SAY ABOUT DISCHARGES
For a classified installation requiring authorisation, the order of 2 February 1998 sets the basic rule: discharged effluent must be below 30 °C. In shellfish waters, the discharge must not raise the temperature of the receiving water by more than 2 °C. The prefectoral permit then sets site-specific values, and sea discharges also fall under the water act.
Meeting 30 °C at the outfall does not tell the whole story. In a port basin, water is renewed less than in open sea: the warm plume can build up, especially in summer, when the sea is already warm and cooling demand peaks.
QUESTIONS AN APPLICATION SHOULD ADDRESS
- Thermal discharge. Pumped flow, temperature difference between intake and outfall, plume modelling in the basin in summer and winter, and post-commissioning monitoring.
- The intake. Depth, intake velocity, screening, and the effect on marine organisms drawn in.
- Circuit maintenance. Seawater fouls and corrodes exchangers. What anti-fouling treatment is planned, with which products and discharges?
- Back-up chillers. How many days a year, what capacity, what power use, which refrigerants? They determine real performance during heatwaves.
- Noise in a port area. Port background noise is high and variable. The emergence rule compares noise with and without the installation at homes, so the baseline must be measured at the nearest homes, day and night, including when port activity is low.
- Sea level rise and storms, for a building partly over water.
- Heat reuse. Seawater removes the heat, but French law also requires waste heat recovery from 1 MW. Could a network such as Thassalia or Massileo benefit?
WHAT ANYONE CAN DO
The Saumaty environmental authorisation file is available online and anyone can submit comments until 18 February 2027. Public meetings are planned on 26 November 2026 and 3 February 2027. The consultation is not a vote: the inquiry officer then issues a report and reasoned conclusions, and the prefect decides.
We follow the project in our opposition tracker. On noise, see data center noise in France.
Sources: Made in Marseille (19/11/2026); order of 2 February 1998 on emissions from classified installations requiring authorisation; Connaissance des énergies (Thassalia); EDF (Massileo); Interxion / Digital Realty (River Cooling).
THE GRIDREADINESS MONTHLY LETTER
Grid connection, equipment and data center projects in France: what matters, once a month.
Your email is used only for this letter. Legal notice.
Thank you, you are subscribed.
Sending failed. Email fred@gridreadiness.com.
FREQUENTLY ASKED QUESTIONS
How does a seawater-cooled data center work?
Seawater is pumped through heat exchangers, absorbs heat from a closed freshwater loop and is discharged slightly warmer. Seawater does not touch the servers and no water is evaporated. In summer, back-up chillers are often needed.
What temperature can a data center's discharge water reach in France?
For a classified installation requiring authorisation, the basic rule is a discharge below 30 °C; in shellfish waters, the discharge must not raise the water temperature by more than 2 °C. The permit sets site-specific values.