Cooling a data center with seawater instead of chillers or evaporative towers is attractive: it saves electricity and uses no freshwater. It remains rare in France. Data4's project in the port of Saumaty, Marseille, put to public consultation on 18 November 2026, brings it back into focus. Here is how this type of cooling works, what French rules say about discharges, and the questions an application should address.

THE PRINCIPLE

Seawater is pumped through heat exchangers, where it absorbs heat from a closed freshwater loop, then is discharged slightly warmer. The closed loop cools the server rooms. Seawater never touches the servers and no water is evaporated.

The process depends entirely on sea temperature. In Marseille, the Thassalia marine geothermal plant draws water at 7 metres depth, at about 14 °C in winter and 22 °C in summer. In summer this water alone is no longer enough to cool IT equipment: back-up chillers are needed, which use electricity and make noise.

WHAT ALREADY EXISTS IN MARSEILLE

WHAT THE RULES SAY ABOUT DISCHARGES

For a classified installation requiring authorisation, the order of 2 February 1998 sets the basic rule: discharged effluent must be below 30 °C. In shellfish waters, the discharge must not raise the temperature of the receiving water by more than 2 °C. The prefectoral permit then sets site-specific values, and sea discharges also fall under the water act.

Meeting 30 °C at the outfall does not tell the whole story. In a port basin, water is renewed less than in open sea: the warm plume can build up, especially in summer, when the sea is already warm and cooling demand peaks.

QUESTIONS AN APPLICATION SHOULD ADDRESS

WHAT ANYONE CAN DO

The Saumaty environmental authorisation file is available online and anyone can submit comments until 18 February 2027. Public meetings are planned on 26 November 2026 and 3 February 2027. The consultation is not a vote: the inquiry officer then issues a report and reasoned conclusions, and the prefect decides.

We follow the project in our opposition tracker. On noise, see data center noise in France.

Sources: Made in Marseille (19/11/2026); order of 2 February 1998 on emissions from classified installations requiring authorisation; Connaissance des énergies (Thassalia); EDF (Massileo); Interxion / Digital Realty (River Cooling).

THE GRIDREADINESS MONTHLY LETTER

Grid connection, equipment and data center projects in France: what matters, once a month.

Your email is used only for this letter. Legal notice.

Thank you, you are subscribed.

Sending failed. Email fred@gridreadiness.com.

FREQUENTLY ASKED QUESTIONS

How does a seawater-cooled data center work?

Seawater is pumped through heat exchangers, absorbs heat from a closed freshwater loop and is discharged slightly warmer. Seawater does not touch the servers and no water is evaporated. In summer, back-up chillers are often needed.

What temperature can a data center's discharge water reach in France?

For a classified installation requiring authorisation, the basic rule is a discharge below 30 °C; in shellfish waters, the discharge must not raise the water temperature by more than 2 °C. The permit sets site-specific values.