A new question is coming up in public meetings on data centers: do cooling fluids contain PFAS, the "forever chemicals"? The short answer: often yes under the definition used at EU level, but not always, and the rules are still being decided. This article sets out what is known as of 19 November 2026, what remains uncertain, and the questions to ask a developer.
TWO CIRCUITS NOT TO CONFUSE
- The water loop, often water with glycol, circulating between the halls and the cooling plant. It is not a PFAS.
- The refrigerant, inside chillers, used to produce cold when outside air is not enough. This is what may be a fluorinated gas.
A refrigerant is a gas. If it leaks, it goes into the atmosphere, not directly into groundwater. The environmental question is what happens to it next.
WHICH FLUIDS ARE PFAS?
The EU PFAS restriction proposal, submitted by five countries (Denmark, Germany, the Netherlands, Norway, Sweden), uses a broad definition: any substance with at least one fully fluorinated carbon atom. Under this definition:
| Family | Examples | PFAS under the EU proposal's definition |
|---|---|---|
| HFC | R-134a, R-125 (in R-410A) | Yes |
| HFC | R-32 | No |
| HFO | R-1234ze, R-1234yf | Yes |
| Natural refrigerants | Propane (R-290), ammonia (R-717), CO₂ (R-744), water | No |
Blends follow their components. Some fluorinated fluids used for immersion cooling are also covered.
THE TFA ISSUE
Once in the atmosphere, several fluorinated gases break down into trifluoroacetic acid (TFA), the smallest PFAS, which returns with rain and accumulates in water and soil. The share of TFA formed varies widely: almost complete for R-1234yf, much lower for R-1234ze. In June 2026, the Risk Assessment Committee of the European Chemicals Agency (ECHA) recommended classifying TFA as toxic for reproduction and as persistent and mobile. The European Commission has yet to adopt this classification.
WHAT APPLIES TODAY
- The EU F-gas Regulation (Regulation (EU) 2024/573, in force since 11 March 2024): a phase-down of HFCs to a phase-out in 2050, bans on certain equipment depending on the fluid's warming potential, and leak checks from 5 tonnes CO₂ equivalent for HFCs and from 1 kg for HFOs, with mandatory leak detection above 500 tonnes CO₂ equivalent (HFC) or 100 kg (HFO).
- French classified installations rules: above 300 kg of fluid in equipment of more than 2 kg each, a site falls under heading 1185 (declaration with periodic inspection).
WHAT IS NOT YET DECIDED
The EU PFAS restriction has not been adopted. ECHA's Risk Assessment Committee adopted its opinion in March 2026, and the draft opinion of the Socio-Economic Analysis Committee was put to consultation in spring 2026. The process is still under way at ECHA; the European Commission must then propose a text to be discussed with Member States. There is no application date and no final list of derogations, and industry has asked for exemptions for refrigerants. It would therefore be inaccurate to say these fluids are "banned", or that they will not be affected.
QUESTIONS TO ASK THE DEVELOPER
- What is the cooling system, and how many hours a year do the chillers actually run?
- Which refrigerant, what total quantity, and is it a PFAS under the EU definition?
- Was a natural refrigerant or dry cooling without chillers considered? Why was it ruled out?
- What leak detection, how often are checks carried out, and will annual top-up quantities be disclosed?
- What is the plan if the EU restriction is adopted during the installation's lifetime?
See also the questions residents ask about a data center and our opposition tracker.
Situation as of 19 November 2026. This article is an information summary, not legal advice. Sources: Regulation (EU) 2024/573 on fluorinated greenhouse gases; ECHA, universal PFAS restriction proposal and RAC and SEAC opinions (2026); ECHA RAC opinion on TFA classification (June 2026); French classified installations nomenclature, heading 1185.
THE GRIDREADINESS MONTHLY LETTER
Grid connection, equipment and data center projects in France: what matters, once a month.
Your email is used only for this letter. Legal notice.
Thank you, you are subscribed.
Sending failed. Email fred@gridreadiness.com.
FREQUENTLY ASKED QUESTIONS
Are data center refrigerants PFAS?
Many are under the EU restriction proposal's definition: HFCs such as R-134a and HFOs such as R-1234ze. R-32 and natural refrigerants (propane, ammonia, CO₂, water) are not. The glycol water loop in the halls is not a PFAS.
Are fluorinated refrigerants banned in Europe?
Not at this stage. The F-gas Regulation phases down HFCs and bans some equipment, but the EU PFAS restriction has not been adopted and its application to refrigerants is not yet decided.