For forty years, a demand facility connected to the transmission system had one main obligation: not to disturb it. The rules now being written in Europe add another, until now reserved for power stations: stay connected through a fault and contribute to the stability of the system it depends on. For a data center, that reaches into the heart of its electrical architecture.
Two documents measure the shift. The report published by ENTSO-E on 8 May 2026, giving the European transmission system operators' view. And modification MPID345 to the Irish Grid Code, filed by EirGrid, which to our knowledge is the first European text turning that expectation into enforceable requirements.
WHAT GRID OPERATORS ARE SEEING
The ENTSO-E report describes four behaviours that set a large data center apart from a conventional industrial consumer.
The first is the UPS. Designed to protect the IT load, it switches to battery at the first sign of a voltage dip. From the grid's point of view, that means losing hundreds of megawatts of demand at once, precisely when the system is already disturbed. The equipment does exactly what it was installed to do, and that is the problem.
The second is AI workloads, which can swing by tens of megawatts within milliseconds. The grid sees a stream of unpredictable load-shedding and load-application events.
The third is subtler: periodic training loads can excite the electromechanical modes of the power system. Some sub-synchronous oscillations are not detectable by standard supervision tools.
The fourth concerns voltage. A site drawing constant power can deepen a voltage dip before disconnecting. And because reconnection is not standardised, repeated disconnect and reconnect cycles can follow.
We described the phenomenon from inside the data hall in our article on GPU load oscillations. The ENTSO-E report reads it the other way round, from the grid.
THE LEGAL FINDING: A FRAMEWORK WRITTEN FOR A DIFFERENT KIND OF DEMAND
The European Union has three connection codes: RfG for generation, DCC for demand, and one for HVDC. The report notes that the framework applying to demand connections rests on an assumption of predictable, steady demand, which data centers break. It adds that in most European jurisdictions no standard currently requires grid-supportive behaviour from a large demand facility during a fault.
The report does not go through the DCC clause by clause. It does set the direction clearly: updated connection requirements, developed in a coordinated way across Europe to avoid fragmentation.
Oscillation damping, tuning power electronics to suppress rather than excite them
Voltage control and reactive power at the connection point
Fault ride-through, meaning staying connected during the dip
RoCoF withstand, including UPS and protection logic
Controlled post-fault active power recovery
IRELAND HAS ALREADY WRITTEN THE TEXT
On 17 November 2025 EirGrid filed a modification to the Irish Grid Code, referenced MPID345, covering fault ride-through, rate of change of frequency and post-fault active power recovery for transmission-connected demand facilities. It amends sections CC.7.4.2 to CC.7.4.4 and requires approval by the Irish regulator.
The work went deep. EirGrid published a study assessment guide for fault ride-through and active power recovery in March 2026, a compliance and derogation framework in April 2026, and an update assessing alternative solutions in June 2026. The vocabulary says a great deal: UPS now appears in the acronym list of grid code documents.
What happened in Ireland is worth noting. The text came after real events on the grid and after years of connection pressure around Dublin. The incidents came first, the rules followed.
WHAT THIS CHANGES FOR A FRENCH PROJECT
In France, the requirements applying to demand facilities flow from EU regulation 2016/1388 and the decree of 9 June 2020. They require a facility not to disturb the grid or other users, and the connection agreement then sets out, site by site, the expected performance. They were written for conventional industrial consumers.
The French direction is nonetheless readable. Since October 2025, RTE, Data4 and Schneider Electric have been running a demonstrator at the Marcoussis campus analysing how a data center behaves under disturbances, in part to inform future technical connection requirements. The question is not whether those requirements will tighten, but when, and how far.
For a developer the consequence is concrete: a data center energised in 2030 will live most of its life under rules that are not yet written. The electrical architecture is decided now; the requirements will keep evolving for decades. And the design question that follows is not obvious: which asset provides grid support? The UPS protecting the IT load, dedicated storage at the connection point, or an asset built to do both? The most intuitive answer, the existing UPS, also asks a piece of equipment to perform a grid function it was never designed for.
WHAT TO PUT IN A FILE NOW
None of this is asked for today in a French connection request. Offering it changes the conversation with the grid operator: the project stops being a load to connect and becomes a site whose behaviour is known. Expert: Xavier Watrelos, for HV grid connection, the PTF request file and how the site behaves electrically.
OUR TAKEAWAY
France keeps its advantage on capacity and on the cost of electricity. The next differentiator will be how sites behave electrically. The countries that have already written their rules, Ireland first among them, did so under the pressure of incidents. French projects can still anticipate, which is a more comfortable position, provided these questions are raised before design freeze rather than after.
SOURCES
ENTSO-E, "Data centres and the power system: expected trends, challenges and opportunities", May 2026; EirGrid, Grid Code modification proposal MPID345, 17 November 2025, and associated documents of March, April and June 2026; EU regulation 2016/1388; French decree of 9 June 2020 on technical design and operation requirements for grid connection; Data4, announcement of the Marcoussis demonstrator with RTE and Schneider Electric, 29 October 2025.
THE GRIDREADINESS MONTHLY LETTER
Grid connection, equipment and data center projects in France: what matters, once a month.
Your email is used only for this letter. Legal notice.
Thank you, you are subscribed.
Sending failed. Email fred@gridreadiness.com.
FREQUENTLY ASKED QUESTIONS
Do these requirements already apply in France?
No. The current French framework rests on EU regulation 2016/1388 and the decree of 9 June 2020, which require a facility not to disturb the grid but do not require supportive behaviour during a fault. The demonstrator RTE has been running at Marcoussis since October 2025 is aimed in part at informing future requirements.
Why is the UPS a problem for the grid?
Because it does its job. At the first voltage dip it transfers the IT load to battery to protect it. For the grid operator, that appears as a sudden loss of hundreds of megawatts of demand during a disturbance.
Should a developer wait for the texts before acting?
The electrical architecture is decided before the texts and lasts for decades. Describing the load profile, choosing a smoothing strategy and keeping headroom for a grid-support function costs far less at design stage than after energisation.