GRID DEPLOYMENT
RISK AUDIT

This is a sample output. All data is illustrative. Your report is based on real manufacturer contacts and live grid operator data.

SAMPLE
GRIDREADINESS.COM

GRID DEPLOYMENT
RISK AUDIT

Ref: GR-2026-047
Issued: 26 May 2026
Prepared by: Fred ARNAUD
Classification: CONFIDENTIAL

01 — Project Overview

80 MW
Required Power
Grand Est
Region, France
Q3 2028
Target Commissioning
AI DC
Project Type
Identified
Site Status
Not Placed
Transformer Order

02 — Risk Scorecard

Grid Connection Feasibility
STRONG 82/100
Transformer Availability
MODERATE 58/100
Equipment Supply Risk
HIGH RISK 38/100
Timeline Viability
VIABLE 75/100
Power Price Stability
EXCELLENT 91/100

03 — Grid Infrastructure Analysis

Nearest HV Substation
2.4 km · 225kV RTE
Available Substation Capacity
Confirmed 120 MW available
RTE Connection Study Timeline
Est. 12–18 months from application
Grid Operator
RTE (Réseau de Transport d'Électricité)
Estimated Energisation Date
Q3 2028 — ACHIEVABLE
Power Price (nuclear baseload)
€50–70/MWh — EU best

04 — Transformer Procurement Analysis

Required Specification
2 × 50 MVA, 225/33kV, IEC 60076
Recommended Manufacturer
Efacec (Portugal) — 24–28 months
Alternative Option
Pauwels (Belgium) — 26–32 months
Order Deadline for Q3 2028
IMMEDIATE — slots available now
Estimated Unit Cost
€350,000–€500,000 per unit
Used Market Alternative
1 unit identified — inspection required

05 — Key Risk Flags

CRITICAL

Transformer order not placed. Efacec Q3 2028 delivery slots are currently available but being absorbed by North American buyers. Any delay beyond June 2026 risks pushing delivery to Q4 2028 or later, jeopardising the commissioning date.

MODERATE

RTE connection study not initiated. Application should be submitted within 30 days to maintain Q3 2028 timeline. Substation capacity is confirmed available but will not be reserved without formal application.

LOW

Switchgear lead time manageable. MV switchgear for this specification is available at 18–22 months from Schneider Electric France. This can be ordered after RTE study confirmation without risking the timeline.

06 — Deployment Decision

✓ PROCEED — WITH IMMEDIATE ACTION

This site is viable for Q3 2028 commissioning. The grid infrastructure, power price and site characteristics are strongly favourable. The project faces one critical risk: transformer procurement must be initiated immediately. Efacec delivery slots for Q3 2028 exist today but will not exist in 90 days at current absorption rates.

  • Contact Efacec commercial team this week — reference specification 2 × 50 MVA, 225/33kV, IEC, Q3 2028 delivery
  • Submit RTE connection study application within 30 days
  • Commission independent DGA testing on identified used unit as backup option
  • Engage regional development agency (ADIRA Grand Est) for loi industrie verte fast-track qualification
GridReadiness · gridreadiness.com · © 2026
This report is based on conditions at time of preparation. GridReadiness accepts no liability for procurement decisions.

THIS IS WHAT YOU RECEIVE

A structured Go/Proceed/Reassess decision framework based on real manufacturer data and live grid conditions. Delivered in 72 hours.