KEY METRICS — JUNE 2026

AI Infrastructure Europe — Status Report
EU transformer lead times: Efacec 20–28m · Pauwels 24–32m · ABB/Siemens 48–60m
France RTE brownfield: 18–36 months
European grid requests: 280 GW (90% of EU total demand) — Barclays/Datacenter Dynamics
Closed markets: Ireland 2028 · Netherlands 2030 · Frankfurt 2030
Open market: France — 4 fast-track sites + 63 pre-qualified + 40+ brownfield
Choose France 2026: €80B+ committed · SoftBank · Ardian · Nebius · Digital Realty

MONTHLY LEAD TIME TRACKER

GridReadiness tracks transformer lead times monthly across 14 EU manufacturers in 6 countries. The tracker is available to newsletter subscribers and consulting clients. Subscribe at gridreadiness.com to receive the monthly European Transformer Lead Time Index.

THE INTELLIGENCE LIBRARY

46 articles on AI infrastructure power bottlenecks — transformer procurement, RTE connections, brownfield sites, hyperscaler strategies, policy signals. Browse the full library →

SUBSCRIBE FOR MONTHLY UPDATES

Subscribe to the GridReadiness newsletter → Monthly transformer lead times, brownfield site availability, hyperscaler moves, policy signals. B2B intelligence only. No spam.

GET A GRID DEPLOYMENT ASSESSMENT

Fixed price · 72-hour delivery · Go/No-go verdict for your specific project.

Request Grid Assessment →

GridReadiness · frederic_arn@yahoo.fr · June 2026