Transformer lead times have received significant attention in the AI infrastructure press. The switchgear shortage has not. This is a mistake: medium and high voltage switchgear, circuit breakers and protection relays face lead times that are nearly as long as transformers — and without them, a transformer is useless.

WHAT SWITCHGEAR IS AND WHY IT MATTERS

Switchgear is the collective term for the electrical equipment used to switch, protect and isolate electrical circuits. In a data center power infrastructure, it includes:

A data center cannot operate without switchgear. It is as essential as the transformer — and currently almost as difficult to procure.

CURRENT LEAD TIMES

Switchgear Lead Times — May 2025 MV switchgear (GIS, AIS, 12–36kV): 18–36 months
HV circuit breakers (72–145kV): 24–42 months
Protection relays and automation systems: 12–24 months
Key manufacturers: Schneider Electric, ABB, Siemens, Eaton, Lucy Electric

WHY SWITCHGEAR IS TIGHT

The switchgear shortage has the same root cause as the transformer shortage: a sudden surge in demand from data centers, renewable energy infrastructure and grid modernisation, hitting manufacturing capacity that was sized for pre-AI demand levels.

Additionally, switchgear modernisation across European and North American utilities — driven by aging infrastructure and grid digitalisation programmes — is consuming a significant share of production capacity independently of the data center surge.

THE COMPOUND PROBLEM

A data center project that successfully secures transformer delivery in 30 months still needs switchgear. If the switchgear lead time is 36 months, the transformer arrives at a site that cannot yet use it. The critical path is determined by the longest lead time item — and developers who have focused only on transformers may be surprised to find switchgear is their actual bottleneck.

Complete Power Equipment Lead Times — 2025 Large power transformer: 48–60 months (major OEMs)
MV switchgear panels: 18–36 months
HV circuit breakers: 24–42 months
Standby generators: 12–18 months
UPS systems: 6–12 months
All items must arrive before energisation is possible

SOURCING STRATEGIES

Several strategies can reduce switchgear lead times: