In the Paris region (Île-de-France), a data center above 5,000 m² cannot obtain its building permit without prior approval ("agrément") from the regional prefect. Since summer 2026, this approval has been assessed against more precise criteria, and waste heat recovery now carries real weight. What was often a statement of intent in applications is becoming a point of review, and sometimes a ground for refusal or challenge.
THE AGRÉMENT: A REQUIRED STEP IN THE PARIS REGION
The business real estate approval is set out in articles L.510-1 et seq. of the French planning code. It is granted by the prefect of the Île-de-France region. Data centers require it once they exceed 5,000 m² of floor area. It is a precondition for the building permit application, and it must comply with the regional master plan (SDRIF-E).
WHAT THE SDRIF-E SAYS
The SDRIF-E, approved on 10 June 2025, includes an orientation dedicated to data centers (OR 126). New sites should be located primarily in existing business parks, limit their environmental impact, take local grid capacity into account, and recover their waste heat.
WHAT THE STATE HAS ASKED FOR SINCE JULY 2026
The regional environment directorate (DRIEAT) published a guidance note in June 2026 that applies to approval applications filed from 1 July 2026. On waste heat, it asks for:
- a detailed study on maximising waste heat recovery;
- where the study is positive, a commitment in principle from a heat user, public or private;
- a preference for sites near district heating networks or heat-consuming facilities;
- in the dense core of the region, a recovery target of around 20% of the electricity used, with heat exchangers planned from the design stage.
The same note asks for realistic power sizing, with closer scrutiny above 40 MW where the grid is constrained.
WHAT IS HAPPENING ON THE GROUND
Two recent events reported in the press show that this criterion is now examined closely. In Réau (Seine-et-Marne), an approval was reportedly refused in early October 2026 for a data center project, on the ground that the municipality lacked the technical and economic conditions for a heating network. In the same municipality, the environmental federation France Nature Environnement filed an administrative appeal against the approval granted in late July 2026 to Verne's project, disputing in particular the demonstration of heat recovery. To our knowledge these decisions and appeals have not been published at this stage; we follow them in our tracker of consultations, permits and legal challenges.
A NATIONAL OBLIGATION AS WELL
Outside the Paris region there is no agrément, but waste heat recovery remains mandatory. The French energy code (article L.236-2) requires data centers with installed power of at least 1 MW to recover their waste heat, with an energy reuse factor (ERF) of at least 0.20 unless technically or economically impossible.
WHAT IT MEANS FOR A DEVELOPER
- Choose the site with heat in mind. A plot with no heating network or heat user nearby is harder to defend.
- Replace intentions with a study. Heat volumes, temperatures, seasonality, connection cost: authorities expect figures.
- Secure a written commitment. A letter from a future user (municipality, heating network, greenhouses, industry) carries more weight than a list of possible outlets.
- Plan the equipment at design stage. Heat exchangers and pipework cost far less when planned from the start.
- Share real figures early. Power figures that shift over time, or a file perceived as opaque, fuel opposition whatever the merits of the project.
We help developers and local authorities prepare these elements: heat outlet studies, dialogue with potential users, consultation. See our support for local authorities.
Sources: French planning code (art. L.510-1 and R.510-6); DRIEAT guidance note on data center approval applications (June 2026); SDRIF-E approved on 10 June 2025; French energy code (art. L.236-2); press (October and November 2026).
THE GRIDREADINESS MONTHLY LETTER
Grid connection, equipment and data center projects in France: what matters, once a month.
Your email is used only for this letter. Legal notice.
Thank you, you are subscribed.
Sending failed. Email fred@gridreadiness.com.