The French government's 63 pre-qualified AI data center sites are now known to every hyperscaler, infrastructure fund and developer in Europe. They appear in CBRE reports, JLL presentations and Business France pitch decks. They are not a competitive advantage.

MONTHLY BRIEF

Get the GridReadiness Monthly Brief — transformer lead times, brownfield sites, EU grid data. Used by developers, funds and operators evaluating Europe.

Tell us about your project and we'll send you the brief and follow up personally.

No spam. Monthly cadence. Fred replies personally.  · 

What follows is different: a selection of former French industrial sites with existing high-voltage infrastructure that have never been systematically marketed to AI data center developers in English. These sites were built for industries that consumed 10 to 200 MW of electricity — and the grid connections they required are still there.

The Methodology Source 1: BASIAS — 300,000+ former industrial sites nationally inventoried
Source 2: Cartofriches (CEREMA) — 14,300+ characterised brownfield sites
Source 3: RTE network map — HV lines 63kV, 90kV, 225kV, 400kV
Source 4: Local development agency contacts — site availability confirmation
Filter: former industrial sites within 5km of 63kV+ RTE infrastructure
Key insight: no one has crossed these sources specifically for AI data center targeting

CATEGORY 1 — FORMER ALUMINUM SMELTERS (PECHINEY / RIO TINTO ALCAN LEGACY)

Aluminum electrolysis requires more electricity per unit of output than almost any other industrial process — 13,000 to 16,000 kWh per tonne of aluminum produced. French Pechiney smelters consumed 50 to 200 MW each. Every site had a dedicated RTE high-voltage connection. When they closed, the connections remained.

Critical note: several Pechiney sites (Noguères, Lannemezan) have been partially demolished. The HV infrastructure status must be verified site by site. Sites in the French Alps and Pyrenees may have connectivity challenges that urban/industrial zone sites do not.

Former Aluminum Smelters — France (Confirmed Closed) Noguères (Pyrénées-Atlantiques, 64): 66 ha, closed 1991, demolition complete, HV status to verify — Lacq basin, strong industrial support
Lannemezan (Hautes-Pyrénées, 65): closed 2005, Pechiney/Alcan legacy, Hautes-Pyrénées location
L'Argentière-la-Bessée (Hautes-Alpes, 05): closed 1988, partial industrial reconversion underway
Livet-et-Gavet / Rioupéroux (Isère, 38): closed 1990s, Alpine location near Grenoble tech hub
Venthon (Savoie, 73): small site, closed 1983
Saint-Jean-de-Maurienne (Savoie, 73): STILL ACTIVE (Trimet) — potential expansion partner
Dunkerque (Nord, 59): Pechiney/Alcan opened 1991 — port location, nuclear proximity

Assessment: Dunkerque and Lacq basin (Noguères) strongest candidates for AI data center conversion

CATEGORY 2 — EDF BROWNFIELD PROGRAMME (ANNOUNCED + UNANNOUNCED)

EDF has committed to recycling its former industrial portfolio into data center infrastructure. The announced sites (Loire-sur-Rhône, Moselle, Seine-et-Marne) have partners. The unannounced sites do not — yet.

EDF Former Thermal Power Stations — Status as of May 2026 Loire-sur-Rhône (Isère, 38): AMI launched December 2025 — seeking data center developer, EDF foncier
Maxeville / Emile Huchet (Moselle, 57): contracts signed (OpCore, Eclairion) — TAKEN
Seine-et-Marne (77): contracts signed — TAKEN
Cordemais (Loire-Atlantique, 44): coal plant closure planned 2026–2027 — UPCOMING OPPORTUNITY
Le Havre Havre (Seine-Maritime, 76): former SNET thermal, coastal location
Gardanne (Bouches-du-Rhône, 13): former coal plant, Provence location, near Marseille
Montereau (Seine-et-Marne, 77): former fuel oil plant on Seine river — cooling water available
Vitry-sur-Seine (Val-de-Marne, 94): former EDF thermal — suburban Paris location

Key contact: EDF Développement Durable / EDF Foncier — appels à manifestation d'intérêt

CATEGORY 3 — FORMER STEEL AND METALLURGY SITES

The Lorraine steel belt and Nord industrial corridor contain France's largest concentration of former heavy industry sites. A major discovery in this research: Data4 has just announced a project on the former Usinor site at Escaudain (Hauts-de-France) — 38 hectares, first service from 2030. This validates the category. Similar sites in the same region remain available.

Former Steel Sites — France (Selected) Escaudain / friche Usinor (Nord, 59): Data4 project announced — 38ha, 2,400 jobs, 300M EUR RTE investment — TAKEN but confirms category
Florange (Moselle, 57): former ArcelorMittal blast furnaces, large site, Lorraine
Gandrange (Moselle, 57): former Arcelor steel, cleared land
Thionville corridor (Moselle, 57): multiple former steel sites, RTE infrastructure dense
Pompey (Meurthe-et-Moselle, 54): former steel rolling mills, Moselle river location
Montereau-Fault-Yonne (Seine-et-Marne, 77): former Vallourec/Mannesmann tubes
Aulnoye-Aymeries (Nord, 59): former Vallourec, near Belgian border, good grid

Regional contact: ADIRA Grand Est · Hauts-de-France Invest & Expand

CATEGORY 4 — FORMER CHEMICAL INDUSTRY SITES

Chemical plants are among the most grid-intensive industrial facilities outside of metals production. The Lacq basin (Pyrénées-Atlantiques) is particularly significant: over 200 hectares of former industrial land available after the closure of Pechiney (1991), Celanese (2009) and Yara (2018). The local authority has been actively seeking new industrial uses and has existing RTE infrastructure from the gas-to-electricity conversion era.

Former Chemical Sites — France (Selected) Lacq / Mourenx basin (Pyrénées-Atlantiques, 64): 200+ ha, former Pechiney + Celanese + Yara, active RTE infrastructure, CCLO manages foncier — PRIORITY CANDIDATE
Carling / Saint-Avold (Moselle, 57): former Total Petrochemicals, large industrial site, RTE dense Moselle
Feyzin (Rhône, 69): former Total refinery adjacent, south Lyon corridor
Saint-Auban (Alpes-de-Haute-Provence, 04): former electrolysis (now Arkema) — partial availability
Pont-de-Claix (Isère, 38): former chemical complex near Grenoble
Salindres (Gard, 30): Pechiney/Alcan heritage site, southern France

Key contacts: CCLO (Communauté de Communes de Lacq-Orthez) · Hautes-Pyrénées Invest

CATEGORY 5 — FORMER MILITARY BASES AND DGA SITES

Post-Cold War military restructuring left France with dozens of former bases containing industrial-grade electrical infrastructure — radar installations, aircraft maintenance workshops and armament facilities all required dedicated HV connections. Government ownership often simplifies acquisition vs. private brownfield.

Former Military Sites — France (Selected Candidates) Base aérienne 128 Metz-Frescaty (Moselle, 57): closed 2011, large site, Moselle industrial corridor
Base aérienne 103 Cambrai (Nord, 59): closed 2012, Hauts-de-France location
Base aérienne 133 Nancy-Ochey (Meurthe-et-Moselle, 54): partial closure, Grand Est
Former DGA Bourges (Cher, 18): armament research facility, central France
Multiple former OTAN bases, Alsace (Bas-Rhin, 67): cross-border connectivity

Key contact: France Domaine (state property agency) · local prefectures

CATEGORY 6 — FORMER PAPER MILLS

Paper production is highly electricity-intensive — large mills consumed 20 to 80 MW. Normandie and Alsace have the highest concentration of former paper industry sites in France, often with existing 63kV connections.

Former Paper Mill Sites — France (Selected) Papeteries de la Seine / Alizay (Eure, 27): former International Paper, Normandie — SIGNIFICANT SITE
Stracel (Bas-Rhin, 67): former Strasbourg paper mill, Rhine river, Alsace
Schweitzer / Munster (Haut-Rhin, 68): former specialty paper, Alsace valleys
Chapelle Darblay / Grand-Couronne (Seine-Maritime, 76): former UPM, near Rouen port
Darblay / Corbeil-Essonnes (Essonne, 91): suburban Paris, Seine river — high connectivity

Note: Alizay (Eure) is a confirmed priority — former IP mill, large site, Normandie fiber hub nearby

CATEGORY 7 — FORMER AUTOMOTIVE PLANTS

Large automotive factories — particularly first-generation assembly plants built in the 1960s-1970s — have significant electrical infrastructure and available land. The Renault Flins reconversion program is particularly advanced.

Former Automotive Sites — France (Selected) Renault Flins (Yvelines, 78): active reconversion (RE-FACTORY) — partial availability, Seine river, 30km Paris
La Janais / PSA Rennes (Ille-et-Vilaine, 35): Safran taking part — REMAINING LAND still available, 100+ ha
Former PSA Aulnay-sous-Bois (Seine-Saint-Denis, 93): suburban Paris, redevelopment ongoing — data center potential for remaining parcels
Renault Le Mans (Sarthe, 72): foundry and mechanical operations, large industrial site
Former GM / Vauxhall Luton equivalent: Ford Blanquefort (Gironde, 33): closed 2019, near Bordeaux

Note: Flins is most advanced — Renault RE-FACTORY program seeking industrial partners for vacated sections

HIGHEST PRIORITY CANDIDATES — GRIDREADINESS ASSESSMENT

Based on the combination of confirmed HV infrastructure, available land, no competing committed project, and regional development agency support, GridReadiness rates the following as highest priority for immediate investigation:

Priority Tier 1 — Investigate Immediately 1. Lacq / Mourenx basin (64): 200+ ha, CCLO manages, confirmed HV, no committed DC project yet
2. Alizay / Chapelle Darblay (27): large former paper mill, Normandie, fiber connectivity
3. Cordemais (44): EDF thermal closing 2026–2027 — first-mover window opening
4. Escaudain-adjacent sites (59): Data4 confirms the category — neighbouring sites still available
5. Loire-sur-Rhône (38): EDF AMI open — no committed partner announced as of May 2026
Priority Tier 2 — Medium-Term Investigation 6. Carling / Saint-Avold (57): Total Petrochemicals legacy, dense Moselle RTE
7. Florange (57): former ArcelorMittal, Lorraine industrial corridor
8. Dunkerque Pechiney/Alcan adjacent (59): port access + nuclear proximity
9. BA128 Metz-Frescaty (57): military brownfield, government ownership
10. Ford Blanquefort (33): automotive brownfield, near Bordeaux, SW France

HOW TO ACCESS THIS DATABASE

Site-by-site verification on the ground is carried out for GridReadiness clients as part of:

For developers who have exhausted the government's 63-site list and need options that are not already being pursued by Equinix, Microsoft and Nebius simultaneously — this is the intelligence layer that matters.

This database is updated quarterly. Sites change status rapidly as France's data center buildout accelerates. Availability confirmed as of May 2026.